Time and Work is one of important topic in Quantitative Aptitude Section. In Time and Work – Quiz 7 article candidates can find questions with answer. By solving this questions candidates can improve and maintain, speed, and accuracy in the exams. Time and Work - Quiz 7 questions are very useful for different exams such as IBPS PO, Clerk, SSC CGL, SBI PO, NIACL Assistant, NICL AO, IBPS SO, RRB, Railways, Civil Services etc.
Q1
Rajan can do a piece of work in 10 days, Rakesh can do in 12 days and Mukesh do the same work in 15 days. In how many days they can finish the work, working together
Rambabu, Santosh and Sunil can finish a piece of work in 10, 12 and 15 days respectively. If Santosh stops doing the work after 2 days, Rambabu and Sunil will finish the work in
2([latex]\frac{{R}_{b}}{\frac{{S}_{A}}{{S}_{L}}}[/latex]) = 2 ([latex]\frac{{1}{10}}{\frac{\frac{1}{12}}{\frac{1}{15}}}[/latex])
Balance work to be done by [latex]{R}_{b}[/latex])and SL[latex]{S}_{L}[/latex])
= 1 - [latex]\frac {1}{2}[/latex] = [latex]\frac {1}{2}[/latex]
(Rb + SL)’s 1 day work
[latex]\frac {1}{10} + \frac {1}{15} = \frac {3 + 2}{30} = \frac {1}{6}[/latex]
i.e, (Rb + SL) will take 3 days to do [latex]\frac {1}{2}[/latex] of the work
Q3
12 men complete a work in 18 days. 6 days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work ?
Let time taken by A, B, C combined is D days.
i.e, ([latex]\frac{1}{12}[/latex] ÷ [latex]\frac{1}{15}[/latex] ÷ [latex]\frac{1}{20}[/latex])D = 1
([latex]\frac{1}{5}[/latex]) * D = 1
D = 5 days