Broadly, WORK is the quantity of energy transferred from one system to another. Since we are focused on this topic, work is defined as the amount of job assigned or the amount of job actually completed.
Work is always considered as a whole.
There exists an analogy between the time-speed-distance problems and work.
- Work = Distance
- Rate at which work is done = speed
- Number of days required to do the work = Time
Relationships:
- Worker [latex]\propto[/latex] Work ⇒ More workers can do more work and vice-versa.
- Time [latex]\propto[/latex] Work ⇒ In more time, more work can be done and vice-versa.
- Worker [latex]\propto[/latex] [latex]\frac{1}{Time}[/latex] ⇒ More workers can do more work in less time and vice-versa.
Rules to Quickly Solve Problems Related To Time and Work:
Rule 1: If number of days required to complete the work = n, then work that can be done per day = [latex]\frac{1}{n}[/latex], and efficiency is = [latex]\frac{100}{n}[/latex] %
- e.g. If John can finish a work in 10 days, then he will finish [latex]\frac{1}{10}[/latex] part of the work in 1 day.
- e.g. If Mary can finishes [latex]\frac{1}{7}[/latex] part of a work in 1 days, then she will finish the complete work in7 days.
Rule 2: If [latex]M_{1}[/latex] workers can finish [latex]W_{1}[/latex] work in [latex]D_{1}[/latex] number of days, and if [latex]M_{2}[/latex] workers can finish [latex]W_{2}[/latex] work in [latex]D_{2}[/latex] number of days, then,
[latex]\frac{M_{1}D_{1}}{W_{1}}[/latex] = [latex]\frac{M_{2}D_{2}}{W_{2}}[/latex]
Example:
If 3 workers are able to finish in [latex]\frac{1}{3}[/latex] part of work in 6 days, then in how many days can 4 workers finish [latex]\frac{1}{2}[/latex] part of the work?
Solution:
Here [latex]M_{1}[/latex] = 3, [latex]W_{1}[/latex] = [latex]\frac{1}{3}[/latex], [latex]D_{1}[/latex] = 6, and [latex]M_{2}[/latex] = 4, [latex]w_{2}[/latex] = [latex]\frac{1}{2}[/latex]. We have to find out [latex]D_{2}[/latex]. Using Rule 2, we have.
[latex]\frac{M_{1}D_{1}}{W_{1}}[/latex] = [latex]\frac{M_{2}D_{2}}{W_{2}}[/latex] = [latex]\frac{3 \times 6}{\frac{1}{3}}[/latex] = [latex]\frac{4 \times D_{2}}{\frac{1}{2}}[/latex] ⇒ [latex]D_{2}[/latex] = 6.75 Days.
Rule 3: If [latex]M_{1}[/latex] workers can finish [latex]W_{1}[/latex] work in [latex]D_{1}[/latex] number of days after working for [latex]T_{1}[/latex] hours per day, and if [latex]M_{2}[/latex] workers can finish [latex]W_{2}[/latex] work in [latex]D_{2}[/latex] number of days after working for [latex]T_{2}[/latex] hours per day, then,
[latex]\frac{M_{1}D_{1}T_{1}}{W_{1}}[/latex] = [latex]\frac{M_{2}D_{2}T_{2}}{W_{2}}[/latex]
Example:
If 4 men are able to finish in [latex]\frac{1}{5}[/latex] part of work in 4 days after working for 3.5 hours per day, then in how much work can be finished by 2 workers after working 9 hours per day for 5 days?
Solution:
Here [latex]M_{1}[/latex] = 4, [latex]W_{1}[/latex] = [latex]\frac{1}{5}[/latex], [latex]D_{1}[/latex] = 4, [latex]T_{1}[/latex] = 3.5, and [latex]M_{2}[/latex] = 2, [latex]W_{2}[/latex] = ?, [latex]T_{2}[/latex] = 9, [latex]D_{2}[/latex] = 5.
We have to find out [latex]W_{2}[/latex]. UsinRule 3, we have
[latex]\frac{M_{1}D_{1}T_{1}}{W_{1}}[/latex] = [latex]\frac{M_{2}D_{2}T_{2}}{W_{2}}[/latex] = [latex]\frac{4 \times 4 \times 3.5}{\frac{1}{5}}[/latex] = [latex]\frac{4 \times 5 \times 9}{W_{2}}[/latex] ⇒ [latex]W_{2}[/latex] = 1.56 (or) 1 and [latex]\frac{5}{9}[/latex] part more of work.
Rule 4: If A completes a piece of work in ‘x’ days, and B completes the same work in ‘y’ days, then
1. Work done by A in 1 day = [latex]\frac{1}{x}[/latex], and work done by B in 1 day = [latex]\frac{1}{y}[/latex]
2. work done by A and B together in 1 day = [latex]\frac{1}{x}[/latex] + [latex]\frac{1}{y}[/latex]
3. Total days taken to complete the work by A and B working together = [latex]\frac{xy}{x + y}[/latex]
Rule 5: If A alone can do a certain work in ‘x’ days and A and B together can do the same work in ‘y’ days, then B alone can do the same work in
1. work done by A, B and C together in 1 day = [latex]\frac{1}{x}[/latex] + [latex]\frac{1}{y}[/latex] + [latex]\frac{1}{z}[/latex]
2. Total days taken to complete the work by A, B and C working together = [latex]\frac{xyz}{xy + yz + zx}[/latex]
Rule 6: If A alone can do a certain work in ‘x’ days and A and B together can do the same work in ‘y’ days, then B alone can do the same work in [latex]\frac{xy}{x - y}[/latex]
Rule 7: If A and B can do a work in ‘x’ days, B and C can do the same work in ‘y’ days, C and
A can do the same work in ‘z’ days. Then total days taken, when A, B and C work together = [latex]\frac{2xyz}{xy + yz + zx}[/latex]
Rule 8:
- Work of 1 day = [latex]\frac{Total \ work}{Total \ no.of \ working \ days}[/latex]
- Total work = (Work of 1 day) × (Total no. of working days)
- Remaining work = 1 - (Work done)
- Work done by A = (Work done in 1 day by A) × (Total no. of days worked by A)
Rule 9: If A can finish [latex]\frac{m}{n}[/latex] part of the work in D days, then total days taken to finish the work by A = [latex]\frac{n}{m} \times D[/latex].
Rule 10: If A can do a work in ‘x’ days and B can do the same work in ‘y’ days and when they
started working together,
- A left the work ‘m’ days before completion, then total days taken to complete the work is [latex]\frac{(x + m)y}{x + y}[/latex]
- B left the work ‘m’ days before completion, then total days taken to complete the work is [latex]\frac{(y + m)x}{x + y}[/latex]
Rule 11: A and B together can finish a certain work in ‘a’ days. They worked together for ‘b’ days and then B (or A) left the work. A (or B) finished the rest work in ‘d’ days, then total days taken by A (or B) alone to complete the work is [latex]\frac{ad}{a - b}[/latex] (or [latex]\frac{bd}{a - b})[/latex].
Let's see some examples for applying these rules:
Example 1:
A, B and C can do a work in 6, 8 and 12 days respectively. Doing that work together they get an
amount of Rs. 1550. What is the share of B in that amount?
Solution:
A’s share : B’s share : C’s share
= (B’s time × C’s time) : (A’s time × C’s time) : (A’s time × B’s time)
= 96 : 72 : 48
= 4 : 3 : 2
∴ B’s share = [latex]\frac{1550}{9} \times 3[/latex]= Rs. 516.66.
Example 2:
Lita can complete a piece of work in 5 days, but with the help of her son she can do it in 3 days.
Find the time taken by the son alone to complete the work.
Solution:
Use RULE 6! We have x = 5 and y = 3. Then time taken by the son alone to complete the work alone = [latex]\frac{xy}{x - y}[/latex] = [latex]\frac{5 \times 3}{5 - 3}[/latex] = 7.5days.
Example 3:
Two pipes can fill the cistern in 10 hrs and 12 hrs respectively, while the third pipe can empty it
in 20 hrs. Simultaneously, if all the pipes are opened then the cistern will be filled in how many
hours?
Solution:
Use RULE 5 (1)! We have x = 10, y = 12, and z = 20. Then time taken by the pipes
when opened together = [latex]\frac{1}{\frac{1}{10} + \frac{1}{12} - \frac{1}{20}}[/latex] = 7.5 hours.
Example 4:
If machine X can produce 1,000 bolts in 8 hours and machine Y can produce 1,000 bolts in 24 hours. In how many hours can machines X and Y, working together at these constant rates, produce 1,000 bolts?
Solution:
Total work of X and Y: [latex]\frac{1}{8}[/latex] + [latex]\frac{1}{24}[/latex] = [latex]\frac{1}{6}[/latex], Therefore, Working together, machines X and Y can produce 1,000 bolts in 6 hours.