Quantitative Aptitude - SPLessons

SSC CPO Time and Work Quiz 5

Home > > Tutorial
SPLessons 5 Steps, 3 Clicks
5 Steps - 3 Clicks

SSC CPO Time and Work Quiz 5

shape Introduction

SSC CPO Time and Work Quiz 5 is important for exams such as IBPS, RRB, SBI, IPPB, LIC AAO, GIC AO, UIIC AO, NICL AO, etc. SSC CPO Time and Work Quiz 5 will help you to learn more and more concepts in Time and Work. SSC CPO Time and Work Quiz 5 study plan is to utilize time and hard work towards smart work efficiently.

shape Quiz

1. A completes a work in 12 days and B complete the same work in 24 days. If both of them work together, then the number of days required to complete the work will be
    A. 8 days B. 6 days C. 7 days D. 5 days

Answer: Option: A
Explanation: If A can complete a work in x days and B can complete the same work in y days, then, both of them together can complete the work in [latex]\frac{xy}{x + y}[/latex] days Therefore, here, the required number of days = 12 × [latex]\frac{24}{36}[/latex] = 8 days.
2. If 3 persons can do 3 times of a particular work in 3 days, then, 7 persons can do 7 times of that work in
    A. 7 days B. 6 days C. 4 days D. 3 days

Answer: Option: D
Explanation: That is, 1 person can do one time of the work in 3 days. Therefore, 7 persons can do 7 times work in the same 3 days itself.
3. Mangala completes a piece of work in 10 days, Raju completes the same work in 40 days. If both of them work together, then the number of days required to complete the work is
    A. 15 days B. 10 days C. 9 days D. 8 days

Answer: Option: D
Explanation: If A can complete a work in x days and B can complete the same work in y days, then, both of them together can complete the work in [latex]\frac{xy}{x + y}[/latex] days. That is, the required No. of days = 10 × [latex]\frac{40}{50}[/latex] = 8 days.
4. 12 men work 8 hours per day to complete the work in 10 days. To complete the same work in 8 days, working 15 hours a day, the number of men required
    A. 4 days B. 5 days C. 6 days D. 8 days

Answer: Option: D
Explanation: That is, 1 work done = 12 × 8 × 10 Then, 12 8 × 10 = ? × 15 × 8 ? (i.e. No. of men required) = 12 × 8 × [latex]\frac{10}{15}[/latex] × 10 = 8 days.
5. If 5 people undertook a piece of construction work and finished half the job in 15 days. If two people drop out, then the job will be completed in
    A. 25 days B. 20 days C. 15 days D. 10 days

Answer: Option: A
Explanation: That is, half the work done = 5 × 15 × [latex]\frac{1}{2}[/latex] Then, 5 × 15 × [latex]\frac{1}{2}[/latex] = 3 × ? × [latex]\frac{1}{2}[/latex] i.e. 5 × 15 = 3 × ? therefore, ? (No. days required) = 5 × [latex]\frac{15}{3}[/latex] = 25 days.
1. 30 labourers working 7 hours a day can finish a piece of work in 18 days. If the labourers work 6 hours a day, then the number of labourers required to finish the same piece of work in 30 days will be
    A. 15 days B. 21 days C. 25 days D. 22 days

Answer: Option: B
Explanation: That is, 1 work done = 30 × 7 ×18 = ? × 6 × 30 ? (No. of labourers) = 30 × 7 × [latex]\frac{18}{6}[/latex] × 30 = 21
2. If 5 girls can embroider a dress in 9 days, then the number of days taken by 3 girls will be
    A. 20 days B. 10 days C. 14 days D. 15 days

Answer: Option: D
Explanation: That is, 5 × 9 = 3 × ? ? = 5 × [latex]\frac{9}{3}[/latex] = 15 days
3. A and B together can plough a field in 10 hours but by himself A requires 15 hours. How long would B take to plough the same field?
    A. 10 hours B. 20 hours C. 30 hours D. 40 hours

Answer: Option: C
Explanation: If A and B together can do a piece of work in x days and A alone can do the same work in y days, then B alone can do the same work in [latex]\frac{XY}{Y - X}[/latex] days. Therefore, the No. of hours required by B = 10 × [latex]\frac{15}{15}[/latex] – 10 = [latex]\frac{150}{5}[/latex] = 30 hours.
4. If 12 men can do a piece of work in 24 days, then in how many days can 18 men do the same work?
    A. 36 B. 20 C. 18 D. 16

Answer: Option: D
Explanation: 1 work done = 12 × 24 Then, 12 × 24 = 18 × ? days ? days = 12 × [latex]\frac{24}{18}[/latex] = 16.
5. A group of workers accepted to do a piece of work in 25 days. If 6 of them did not turn for the work and the remaining workers did the work in 40 days, then the original number of workers was
    A. 22 B. 21 C. 20 D. 16

Answer: Option: D
Explanation: Let the original number of workers be ‘x’ Then, x × 25 = (x – 6) × 40 25x = 40x - 240 240 = 40x - 25x = 15x x = [latex]\frac{240}{15}[/latex] = 16.
1. If 8 men or 12 women can do a piece of work in 10 days, then the number of days required by 4 men and 4 women to finish the work is
    A. 8 B. 10 C. 12 D. 4

Answer: Option: C
Explanation: 8 men = 12 women 1 woman = [latex]\frac{8}{12}[/latex] men = [latex]\frac{2}{3}[/latex] men 4 women = [latex]\frac{2}{3}[/latex] × 4 men = [latex]\frac{8}{3}[/latex] men 4 men + 4 women = 4 + [latex]\frac{8}{3}[/latex] men = [latex]\frac{20}{3}[/latex] men 1 work done = 8 × 10 8 × 10 = [latex]\frac{20}{3}[/latex] × ?days ? days = 8 × 10 × [latex]\frac{3}{20}[/latex] = 12 days.
2. If 8 men can dig a well in 18 days, then the number of days, 12 men will take to dig the same well will be
    A. 12 days B. 10 days C. 8 days D. 16 days

Answer: Option: A
Explanation: Work done = 8 × 18 Then, 8 × 18 = 12 × ? days ? days = 8 × [latex]\frac{18}{12}[/latex] = 12 days
3. 39 men can repair a road in 12 days working 5 hours a day. In how many days will 30 men working 6 hours peer day complete the work?
    A. 10 B. 13 C. 14 D. 15

Answer: Option: B
Explanation: 1 work done = 39 × 12 × 5 39 × 12 × 5 = 30 × 6 × ? days ? days = 39 × 12 × [latex]\frac{5}{30}[/latex] × 6 = 13 days.
4. A certain number of men can do a work in 40days. If there were 8 men more, it could be finished in 10 days less. How many men were there initially?
    A. 30 B. 24 C. 16 D. 20

Answer: Option: B
Explanation: Let ‘x’ be the initial number of men Then, 1 work done = x × 40 Then, x × 40 = (x + 8 ) (40 – 10) 40x = 30x + 240 10x = 240 Therefore, x = [latex]\frac{240}{40}[/latex] = 24 men.
5. If 4 men or 6 boys can finish a work in 20 days. How long will 6 men and 11 boys take to finish the same work?
    A. 10 days B. 6 days C. 4 days D. 3 days

Answer: Option: B
Explanation: 4 men = 6 boys Then, 1 boy = [latex]\frac{4}{6}[/latex] men = [latex]\frac{2}{3}[/latex] men 11 boys = 2/3 × 11 men = [latex]\frac{22}{3}[/latex] men Then, 6 men + 11 boys = 6 + 22/3 men = [latex]\frac{40}{3}[/latex] men 1 work done = 4 men × 20days That is, 4 × 20 = [latex]\frac{40}{3}[/latex] × ? days ? days = 4 × 20 × [latex]\frac{3}{40}[/latex] = 6 days

Time and Work - Related Information
Time and Work Practice Quiz
Time and Work Practice Set 1
Time and Work Practice Set 2
IBPS RRB Time and Work Quiz Day 1