1. 4 men can complete a piece of work in 5 days. How many men are required to complete 3 times the work in 4 days?
Answer - Option B
Explanation -
Required number of men will be
[latex]\frac {4 * 5 * 3}{4}[/latex] = 15
2. When Ram and Mohan work together, they complete a work in 4 days. If Ram alone can complete this work in 12 days then in how many days Mohan alone can complete this work ?
A. 10 days
B. 8 days
C. 6 days
D. 16 days
Answer - Option B
Explanation -
Let the total work be 12 units such that work done by Ram in one day be 1 unit.
i.e, Work done by Mohan in one day
= [latex]\frac {12}{4}[/latex] - 1 = 2 units.
3. Pipe 'F can fill a tank in 36 hours and pipe 'Q' can fill this tank in 45 hours. If both the pipes are opened simultaneously, then how much time will be taken to fill this tank ?
A. 20 hours
B. [latex] 40 \frac {1}{2}[/latex] hours
C. 9 hours
D. 42 hours
Answer - Option A
Explanation -
Let the capacity of the tank be 180 units i.e, LCM of 36 and 45 such that efficiencies of the two pipes = 5 units and 4 units.
i.e, required time = [latex]\frac {180}{5 + 4}[/latex] = 20hrs
4. To complete a work P takes 50% more time than Q. If together they take 18 days to complete the work, how much time shall Q take to do it?
A. 30 days
B. 35 days
C. 40 days
D. 45 days
Answer - Option A
Explanation -
Let the time taken by P and Q to complete the work alone be 3x and 2x such that total work be 6x units and their respective efficiencies be 2 units and 3 units.
[latex]\frac {6x}{\frac{3}{2}} = 18[/latex]
x = 15
Hence, Q will complete the work in 2x
= 2 × 15 = 30 days
5. Two pipes can fill a tank in 20 minutes and 30 minutes respectively. If both the pipes are opened simultaneously, then the tank will be filled in
A. 10 minutes
B. 12 minutes
C. 15 minutes
D. 25 minutes
Answer - Option B
Explanation -
Let the capacity of the tank be 60 units i.e.
LCM of 20 and 30 such that their respective efficiencies be 3 units and 2 units.
Hence, required time = [latex]\frac {60}{3 + 2}[/latex] = 12 minutes
6. A and B can do a piece of work in 8 days. A alone can do the same work in 12 days. The number of days in which B alone can do the same work is
Answer - Option B
Explanation -
Let the total work be 24 units i.e. LCM of 8 and 12.
work done by A and B in one day = [latex]\frac {24}{8}[/latex] = 3units
and that by A alone in one day = [latex]\frac {24}{12}[/latex] = 2 units
Hence, work done by B in one day = 1 unit
and required time = [latex]\frac {24}{1}[/latex] = 24 days.
7. P and Q can do a piece of work in 12 days, Q and R in 15 days and R and P in 20 days. In how
many days P alone can do the same work?
A. 15
B. 30
C. 23.5
D. 35
Answer - Option
Explanation -
Let the total work be 60 units i.e. LCM of 12, 15 and 20.
work done by P and Q in one day = [latex]\frac {60}{12}[/latex] = 5 units
and that by Q and R in one day = [latex]\frac {60}{15}[/latex] = 4 units
and that by P and R in one day = [latex]\frac {60}{20}[/latex] = 3 units
Thus, work done by P, Q and R in 1 day = [latex]\frac {5 + 4 + 3 }{2}[/latex] = 6
and that by P in one day = 6 4(work done by Q and R in 1 day) = 2 units
Hence, required time = [latex]\frac {60}{2} = 30[/latex] days
8. A and B can do a piece of work in 24 days. If efficiency of A is double than B, then in how
many days, A alone can do the same work?
Answer - Option B
Explanation -
Set the work done by A and B value in one day be 2 units and 1 units respectively
Total work = 24 × (2 + 1) = 72 units and
Required time = [latex]\frac {72}{2}[/latex] = 36 units
9. P and Q can do a piece of work in 12 days, Q and R in 15 days and R and P in 20 days. In how
many days Q alone can do the same work?
Answer - Option A
Explanation -
Set the total work be 60 unit i.e. LCM of 12, 15 and 20
Work done in one day
by P and Q = 5 units ....(1)
by Q and R = 4 units ....(2)
and by R and P = 3 units ....(3)
Adding (1), (2) and (3) we get
2(P + Q + R) = 5 + 4 + 3
P + Q + R = [latex]\frac {12}{2}[/latex] = 6 units
Thus, work done y Q in one day
= (P + Q + R) – (P + R)
= 6 – 3 = 3 units
Hence, required time = [latex]\frac {60}{3}[/latex] = 20 units
10. A can do a piece of work in 15 days and B ran do the same work in 10 days. If they work together, number of days required to complete the same work is
Answer - Option B
Explanation -
Work done by A in 1day = [latex]\frac {1}{15}[/latex]
Work done by in B in 1day = [latex]\frac {1}{10}[/latex]
Let number of days required = x
[latex](\frac {1}{15} + \frac {1}{10})[/latex]x = 1
i.e, x = 6
11. P and O can do a piece of work in 10 days, Q and R in 12 days and R and P in 15 days. In how many days P alone can do the same work?
A. 24
B. 40
C. 6
D. [latex]\frac{40}{3}[/latex]
Answer - Option A
Explanation -
Let P do work in P days
[latex]\frac{A}{Q}[/latex][ [latex]\frac{\frac{1}{P}}{\frac{1}{Q}}[/latex]] = [latex]\frac{1}{10}[/latex]......(1)
[latex]\frac{\frac{1}{Q}}{\frac{1}{R}}[/latex] = [latex]\frac{1}{12}[/latex].......(2)
[latex]\frac{\frac{1}{P}}{\frac{1}{R}}[/latex] = [latex]\frac{1}{12}[/latex]........(3)
Solving (1), (2), (3)
P = 24
12. A and B can do a piece of work in 24 days. If efficiency of A is double than B, then in how many days B alone can do the same work?
Answer - Option A
Explanation -
Efficiency ratio A : B = 2 : 1
Time ratio A : B = 1 : 2
i.e x & 2x
[latex]\frac{A}{Q}[/latex][latex]\frac{\frac{1}{x}}{\frac{1}{2x}}[/latex]= [latex]\frac{1}{24}[/latex]
x = 36
i.e, B can do work in 2x days = 72
13. P and Q can do a piece of work in 12 days, Q and in R in 15 lays and R and P in 20 days. In how many days R alone can do the same work?
Answer - Option B
Explanation -
Let work done in 1 day by P, Q, R
= [latex]\frac{1}{p}[/latex], [latex]\frac{1}{q}[/latex], [latex]\frac{1}{r}[/latex]
i.e, [latex]\frac{\frac{1}{p}}{\frac{1}{q}}[/latex] = [latex]\frac{1}{12}[/latex]...(1)
[latex]\frac{\frac{1}{q}}{\frac{1}{r}}[/latex] = [latex]\frac{1}{15}[/latex].....(2)
[latex]\frac{\frac{1}{r}}{\frac{1}{p}}[/latex] = [latex]\frac{1}{20}[/latex].....(3)
By solving (4) & (2),
[latex]\frac{1}{r} - \frac{1}{p}[/latex] = [latex]\frac{1}{15} - \frac{1}{12}[/latex]
solving (3) & (4) :
[latex]\frac{2}{r} = \frac{1}{15} - \frac{1}{12} + \frac{1}{20}[/latex] = r = 60
i.e, Number of days in which r can do work = 60
14. A can do a piece of work in 20 day and B can do the same work in 30 days. If they work together the number of days required to do the same work
Answer - Option D
Explanation -
Work done by A in 1 day = [latex]\frac{1}{20}[/latex]
___________ B _______ = [latex]\frac{1}{30}[/latex]
Let no. of days required = D
i.e, ([latex]\frac{\frac{1}{20}}{\frac{1}{30}}[/latex])D = 1
D = 12
15. P and Q can do a piece of work in 10 days. Q and R in 12 days and R and P in 15 days. In how many days R alone can do the same work?,
Answer - Option C
Explanation -
Let R do the work in R days
[latex]\frac{A}{Q}[/latex][latex]\frac{\frac{1}{P}}{\frac{1}{Q}}[/latex]= [latex]\frac{1}{10}[/latex] ....(1)
[latex]\frac{\frac{1}{Q}}{\frac{1}{R}}[/latex]= [latex]\frac{1}{12}[/latex]...(2)
[latex]\frac{\frac{1}{P}}{\frac{1}{R}}[/latex]= [latex]\frac{1}{15}[/latex]...(3)
solving (1), (2), (3):-
R = 40