1. Somu and Ramu can complete the work in 20 and 30 days respectively. In how many days, 50% of the work will get completed?
Answer: Option: B
Explanation:
Let the time taken by Somu= A = 20 days
the time taken by Ramu= B = 30 days
Then number of days to complete 100% of work by Somu+ Ramutogether:
=>[latex]\frac{1}{(A + B)}[/latex] = ([latex]\frac{1}{a}[/latex]) + ([latex]\frac{1}{b}[/latex])
=> [latex]\frac{1}{(A + B)}[/latex] = ([latex]\frac{1}{20}[/latex]) + ([latex]\frac{1}{30}[/latex])
=> [latex]\frac{1}{(A + B)}[/latex] = (30 + 20) / (20 × 30)
=> [latex]\frac{1}{(A + B)}[/latex] = [latex]\frac{50}{600}[/latex]
Taking reciprocal on both sides
A + B = [latex]\frac{600}{50}[/latex]
A + B = 12 days
Thus 100% of the work is completed in 12 days,
50% of the work is completed in {([latex]\frac{12}{100%}[/latex]) × 50%} days = 6 days
2. X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last?
A. 6 days
B. 10 days
C. 15 days
D. 20 days
Answer: Option: B
Explanation:
X’s 1 day’s work = [latex]\frac{1}{20}[/latex]
X’s 4 day’s work = [latex]\frac{1}{20}[/latex] × 4 = [latex]\frac{1}{5}[/latex]
The remaining work = [latex]\frac{4}{5}[/latex]
X and Y’s 1 day work = [latex]\frac{1}{20}[/latex] + [latex]\frac{1}{12}[/latex] = [latex]\frac{4}{30}[/latex] = [latex]\frac{2}{15}[/latex]
Therefore, Both together finish the remaining work in [latex]\frac{4/5}{2/15}[/latex] days
= [latex]\frac{4}{5}[/latex]× [latex]\frac{15}{2}[/latex] = 6 days
Therefore, the total number of days taken to finish the work = 4 + 6 = 10 days.
3. A and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days, A finished he remaining work. In how many days A alone can finish the job?
Answer: Option: D
Explanation:
A + B ‘s 1 day’s work = [latex]\frac{1}{30}[/latex]
Their 20 day’s work = [latex]\frac{1}{30}[/latex] × 20 = [latex]\frac{2}{3}[/latex]
Remaining work = [latex]\frac{1}{3}[/latex]
[latex]\frac{1}{3}[/latex] of the work is done by A in 20 days.
Then, whole work can be done by A in 3 × 20 = 60 days
4. A and B together can do a piece of work in 30 days. A having worked for 16 days, B finishes the remaining work alone in 44 days. In how many days shall B finish the whole work alone?
A. 30 days
B. 40 days
C. 60 days
D. 70 days
Answer: Option: C
Explanation:
A + B’s 1 day’s work = 1/30
i.e. A + B = 1/30 --------- (i)
16 A + 44 B = 1 ------ (ii) ( i.e. 1 = the whole work done)
Multiplying (i) by 16 and subtracting it from (ii), we get
i.e. 16 A + 44 B = 1
16 A + 16B = [latex]\frac{8}{15}[/latex]
28 B = [latex]\frac{7}{15}[/latex]
B = [latex]\frac{1}{60}[/latex] i.e. B’s 1 day’s work = [latex]\frac{1}{60}[/latex]
Therefore, B alone can finish the work in 60 days.
5. A and B together can do a piece of work in 12 days, which B and C together can do in 16 days. After A has been working at it for 5 days and B for 7 days, C finishes it in 13 days. In how many days C alone will do the work?
Answer: Option: B
Explanation:
According to the question,
A + B’s 1 day’s work = [latex]\frac{1}{12}[/latex]
B+ C’s 1 days’ work = [latex]\frac{1}{16}[/latex]
A worked for 5 days, B for 7 days and C for 13 days. So, we can assume that,
A+ B has been working for 5 days and B+ C has been working for 2 days and C alone for 11 days.
i.e. A’s 5 day’s work + B’s 7 day’s work + C’s 13 day’s work = 1
(A+ B)’s 5 days work + (B + C)’s 2 days work + C’s 11 day’s work = 1
[latex]\frac{5}{12}[/latex] + [latex]\frac{2}{16}[/latex] + C’s 11 days work = 1
So, C’s 11 day’s work = 1 – ([latex]\frac{5}{12}[/latex] + [latex]\frac{2}{16}[/latex]) = [latex]\frac{11}{24}[/latex]
C’s 1 days’ work = [latex]\frac{11}{24}[/latex] X [latex]\frac{1}{11}[/latex] = [latex]\frac{1}{24}[/latex]
Therefore, C alone can finish the work in 24 days.