Q1. P takes 6 days less than Q to finish the work individually. If P and Q working together complete the work in 4 days, then how many days are required by Q to complete the work alone ?
A. 7 days
B. 10 Days
C. 5 Days
D. 12 Days
Answer: Option D
Explanation:
[latex]\frac{1}{6}[/latex] + [latex]\frac{1}{12}[/latex]
= [latex]\frac{2 + 1}{12}[/latex] = [latex]\frac{3}{12}[/latex] = [latex]\frac{1}{4}[/latex]
Q2. If X, Y and Z can complete a work in 6 days. If X can work twice faster than Y and thrice faster than Z, then the no of days Z alone can complete the work is
A. 22 days
B. 11 days
C. 33 days
D. 30 Days
Answer: Option C
Explanation:
[latex]\frac{1}{x}[/latex] + [latex]\frac{1}{2x}[/latex] + [latex]\frac{1}{3x}[/latex]
[latex]\frac{1}{6}[/latex]
[latex]\frac{6 + 3+ 2}{6x}[/latex] = 6
[latex]\frac{11}{6x}[/latex] = 6
X = 11
Z = 3x = 33
Q3. If 20 men can do a piece of work in 42 days working 8 hours per day then how many men are required to complete the work, working 5 hours per day in 33 days ?
Answer: Option D
Explanation:
M = [latex]\frac{20*42*8}{5*33}[/latex] = 40.72 = 41
Q4. Three men, four women and six children can complete a work in 7 days. A woman does double the work a man does and a child does half the work a man does. How many women alone can complete this work in 7 days ?
Answer: Option A
Explanation:
2 men = 1 woman
1 man = [latex]\frac{1}{2}[/latex] woman
3 men = [latex]\frac{3}{2}[/latex] women
2 children = 1 man = [latex]\frac{1}{2}[/latex] woman
1 child = [latex]\frac{1}{4}[/latex] woman
6 children = [latex]\frac{6}{4}[/latex] = [latex]\frac{3}{2}[/latex] women
Now, three men, four women and six children
= [latex]\frac{3}{2}[/latex] + 4 + [latex]\frac{3}{2}[/latex] = 3 + 8 + [latex]\frac{3}{2}[/latex]= [latex]\frac{14}{2}[/latex] = 7 women
Q5. If A can complete a work in 30 days, B can do the same work in 36 days, If after doing 5 days, leaves the work.Find in how many days B will do the remaining work ?
A. 22 days
B. 28 days
C. 30 days
D. 36 Days
Answer: Option C
Explanation:
A = [latex]\frac{1}{30}[/latex], B = [latex]\frac{1}{42}[/latex]
6 days work = 5*[latex]\frac{1}{30}[/latex] = [latex]\frac{1}{6}[/latex]
Remaining = [latex]\frac{5}{6}[/latex]
B = 5*[latex]\frac{36}{6}[/latex] = 30