Q1. A is twice efficient as B. A and B together do the same work in as much time as C and D can do together. If the ratio of the number of alone working days of C to D is 2:3 and if B worked 16 days more than C then no of days which A worked alone?
A. 18 Days
B. 20 Days
C. 30 Days
D. 36 Days
Answer: Option A
Explanation :
Assume working days
A = x, B = 2x, C = 2y, D = 3y
[latex]\frac{1}{x}[/latex] + [latex]\frac{1}{2x}[/latex] = [latex]\frac{1}{2y}[/latex] + [latex]\frac{1}{3y}[/latex]
And 2x - 2y = 16
Solving we get x = 18 days.
Q2. A can do a piece of work in 40 days B can do the same piece of work in 60 days. A and B started the work together in the first 15 days A worked with 50% of his efficiency, in the next 15 days B worked with 50% of his efficiency. Now in how many days does the remaining work will be completed if both of them work with their full efficiencies?
A. 1 Day
B. 1.5 Days
C. 2 Days
D. 2.5 Days
Answer: Option B
Explanation :
15*([latex]\frac{1}{80}[/latex] + [latex]\frac{1}{60}[/latex]) + 15*([latex]\frac{1}{120}[/latex]+[latex]\frac{1}{40}[/latex]) + x*([latex]\frac{1}{40}[/latex] + [latex]\frac{1}{60}[/latex]) = 1
x = [latex]\frac{3}{2}[/latex] = 1.5
Total percentage of 3 subjects = 3 × 70 = 210
% in Social = 210 – (60 + 80) = 210 – 140 = 70
Q3. A can do a piece of work in 60 days working 14 hours. B has the same efficiency as of A. A and B started working together. A works 5,6,7 and 8 hours respectively on first four days and repeats the cycle again. Then B has to work how many hours daily if they together completed the work in 80 days?
A. 1 Hour
B. 2 Hours
C. 3 Hours
D. 4 Hours
Answer: Option D
Explanation :
20*[latex]\frac{(5 + 6 + 7 +8 + 4x)}{840}[/latex]= 1
x = 4 hours
Q4. Sruthi, Swetha and Swati together can cut 216 Apples of the same size in 3 hours. Number of Apples cut by Sruthi in 9 hours is same as the number of Apples cut by Swati in 7 hours. In one hour, Swati can cut as many Apples more than Swetha as Swetha can cut more than Sruthi. Then the number of Apples cut by Swetha in one hour?
Answer: Option B
Explanation :
U + v + W = 72
9U = 7W
W - V = V - U
V = 24
Q5. If A and B work together can complete a work in 8/5 days. A started the work alone and completed. 50% of the work and left the work then B started the work alone and finished the rest of work. They took total 5 days to complete the work. Then in how many days B can complete the work if A is more efficient than A?
A. 1 Day
B. 2 Days
C. 3 Days
D. 4 Days
Answer: Option D
Explanation :
[latex]\frac{1}{A}[/latex] + [latex]\frac{1}{B}[/latex] = [latex]\frac{5}{8}[/latex]
[latex]\frac{x}{A}[/latex] + [latex]\frac{y}{B}[/latex] = 1
x + y = 5
y = 4