Q1. If 6 men and 8 boys can do a piece of work in 10 days while 26 men and 48 boys can do the same in 2 days, the time taken by 15 men and 20 boys in doing the same type of work will be:
A. 4 days
B. 5 days
C. 6 days
D. 7 days
Answer: Option A
Explanation:
Let 1 man's 1 day's work = x and 1 boy's 1 day's work = y.
Then, 6x + 8y = [latex]\frac{1}{10}[/latex] and 26x + 48y = [latex]\frac{1}{2}[/latex]
Solving these two equations, we get x = [latex]\frac{1}{100}[/latex] and y = [latex]\frac{1}{200}[/latex]
(15 men + 20 boy)'s 1 day's work = [ [latex]\frac{15}{100}[/latex] + [latex]\frac{20}{200}[/latex]] = [latex]\frac{1}{4}[/latex]
15 men and 20 boys can do the work in 4 days.
Q2. A can do a piece of work in 4 hours; B and C together can do it in 3 hours, while A and C together can do it in 2 hours. How long will B alone take to do it?
A. 8 hours
B. 10 hours
C. 12 hours
D. 24 hours
Answer: Option C
Explanation:
A's 1 hour's work = [latex]\frac{1}{4}[/latex]
(B + C)'s 1 hour's work = [latex]\frac{1}{3}[/latex]
(A + C)'s 1 hour's work = [latex]\frac{1}{2}[/latex]
(A + B + C)'s 1 hour's work = [latex]\frac{1}{4}[/latex] + [latex]\frac{1}{3}[/latex] = [latex]\frac{7}{12}[/latex]
B's 1 hour's work = [ [latex]\frac{7}{12}[/latex] - [latex]\frac{1}{2}[/latex]] = [latex]\frac{1}{12}[/latex]
B alone will take 12 hours to do the work.
Q3. A can do a certain work in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in
A. 15 days
B. 20 days
C. 25 days
D. 30 days
Answer: Option C
Explanation:
(A + B)'s 1 day's work = [latex]\frac{1}{10}[/latex]
C's 1 day's work = [latex]\frac{1}{50}[/latex]
(A + B + C)'s 1 day's work = [latex]\frac{1}{10}[/latex] + [latex]\frac{1}{50}[/latex] = [latex]\frac{6}{50}[/latex] = [latex]\frac{3}{25}[/latex].... (i)
A's 1 day's work = (B + C)'s 1 day's work .... (ii)
From (i) and (ii), we get: 2 x (A's 1 day's work) = [latex]\frac{3}{25}[/latex]
A's 1 day's work = [latex]\frac{3}{50}[/latex]
B's 1 day's work = [latex]\frac{1}{10}[/latex] - [latex]\frac{3}{50}[/latex] = [latex]\frac{2}{50}[/latex] = [latex]\frac{1}{25}[/latex]
So, B alone could do the work in 25 days.
Q4. A machine P can print one lakh books in 8 hours, machine Q can print the same number of books in 10 hours while machine R can print them in 12 hours. All the machines are started at 9 A.M. while machine P is closed at 11 A.M. and the remaining two machines complete work. Approximately at what time will the work (to print one lakh books) be finished ?
A. 11:30 A.M.
B. 12 noon
C. 12:30 P.M.
D. 1:00 P.M.
Answer: Option D
Explanation:
(P + Q + R)'s 1 hour's work = [latex]\frac{1}{8}[/latex] + [latex]\frac{1}{10}[/latex] + [latex]\frac{1}{12}[/latex] = [latex]\frac{37}{120}[/latex]
Work done by P, Q and R in 2 hours = [latex]\frac{37}{120}[/latex] x 2 = [latex]\frac{37}{60}[/latex]
Remaining work = 1 - [latex]\frac{37}{60}[/latex] = [latex]\frac{23}{60}[/latex]
(Q + R)'s 1 hour's work = [[latex]\frac{1}{10}[/latex] + [latex]\frac{1}{12}[/latex] ] = [latex]\frac{11}{60}[/latex]
Now, [latex]\frac{11}{60}[/latex] work is done by Q and R in 1 hour.
So, [latex]\frac{23}{60}[/latex] work will be done by Q and R in [latex]\frac{60}{11}[/latex] x [latex]\frac{23}{11}[/latex] hours = 2 hours
So, the work will be finished approximately 2 hours after 11 A.M., i.e., around 1 P.M.
Q5. 4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it?
Answer: Option B
Explanation:
Let 1 man's 1 day's work = x and 1 woman's 1 day's work = y.
Then, 4x + 6y = [latex]\frac{1}{8}[/latex] and 3x + 7y = [latex]\frac{1}{10}[/latex]
Solving the two equations, we get: x = [latex]\frac{11}{400}[/latex], y = [latex]\frac{1}{40}[/latex]
Hence, 10 women will complete the work in 40 days.